Updates to Altus are deployed quarterly. The updates outlined below have now moved into Altus First Release and are available for your review and testing.
We’ve ranked the updates that have been moved into First Release based on their anticipated complexity/platform impact.
High |
Potential for system impact, test item as a matter of priority, refer to notes |
Medium |
Testing should be undertaken prior to General Availability |
Low |
Testing recommended, item unlikely to cause issues at General Availability |
#15714 |
In key data grids, any custom column can be used to group line items. This works with lookup and option set custom columns on the finance, resource plan, and resource demand grids. |
M |
#23558 |
The summary and dashboard widgets have been extended to support:
To edit window for Numeric Adjustment: |
L |
#21675 |
The resource picker result list now shows the breakdown of available hours for a resource based on the current view of the resource grid. |
L |
A completely new baselining feature has been introduced to Altus in this release with the following functionality in its first instalment:
#22883 |
We have introduced a major new baseline feature which can be used to measure project schedule variance and progress through the project lifecycle. Note: Altus can still be set to use the older Status Update baseline functionality, but this will need to be toggled back on for those organisations who wish to continue using it. We strongly recommend testing the functionality of the Status Update page if it has been modified to suit your needs. *Click image above to view animated screen capture |
H |
Various enhancements have been made to how Altus displays and processes timesheets as well as how Altus integrates timesheet information with other parts of the system.
#22900 |
The default setting for the Timesheet Actuals to Schedule import has been changed to ON when the timesheet mode is Task mode, unless explicitly set otherwise. Note: This avoids the need for PMs to request administrators to switch this feature on manually. |
M |
#22908 |
Date column header for timesheets now displays the day of the week. Note: This reduces confusion for those entering timesheets and lowers the risk that data will be entered into the wrong day column. |
L |
#22626 |
The Timesheet to Finance import is now an import process like the Resource to Finance import process. A banner notification in the Finance app tab alerts users that there are timesheet actuals to import. The import data preview window displays a breakdown of the overall actuals and variances, as well as a breakdown by financial category, with transaction details. *Click image above to view animated screen capture |
M |
#23258 |
Bulk timesheet approval functionality was temporarily removed to avoid some conflicting issues. These issues have now been resolved and bulk timesheet approval has been restored in this release. |
L |
#15796 |
Enhanced timesheet notes interaction for improved workflow efficiency
|
L |
#22260 |
The enterprise calendar field has been hidden for generic resources as it could cause confusion for users. Note: Recommend that there is some check that enterprise calendars for generic resources are not used. |
M |
The following bug fixes have been included in this release and can be reviewed as part of your normal testing process.
#22847 |
Fixed an issue where opening the same timesheet in multiple browser windows/tabs and performing save would create duplicate rows. In instances where duplicate rows are present, a banner is displayed to notify the user to consolidate the data: |
#23490 | Fixed an edge case issue where timesheet can be closed prior to the save being completed, added a prompt to alert user when attempting to close a browser window/tab with saving process in progress. |
#23237 | Resolved an issue with Projects when unlinked from their external system and their tasks are deleted that the project effort and percent complete are reset to 0. |
#8660 | Fixed an issue with calculated project effort and percent complete when project is unlinked from their external system and their tasks are deleted. |
#14311 | Resolved an issue wherein deleting dependencies does not work in some cases. |
#23261 |
Resolved an issue where empty spaces could appear on the right side of Gantt chart when the task timeline is zoomed out in some situations. |
#22877 | Fixed an issue with the finance export to CSV which was ignoring rows with a 0 total. |
#21639 | Resolved an issue with show/hide functionality for the task grid columns. |
#22298 |
Resolved an issue in the Altus Schedule where summary tasks would double count effort from child tasks. Matches effort on the form: |
#22849 | Fixed an edge case problem where the solution could fail to deploy because of Locale issue. |
#22687 | The status update duplication functionality now supports portfolios. |
#21614 | Export to PDF is restored on the task grid with various choices of paper sizes, the default being A0. |
#16194 | Resolved an issue where fulfilling re-submitted resource requests were not showing as Set by approver on the tooltip. |
#21846 | Resolved an issue where the task type of external tasks was forced to be Fixed Duration. |
#21847 |
Resolved an issue where external task field values on the Altus Schedule do not match the values in the external system. Gantt tool now will not recalculate the schedule. |
#22294 | Altus schedule changes when discarded will now return the project form to a saved state. *Click image above to view animated screen capture |
#22834 | Updated Project for the Web Project Dataflow to fix an issue with Percent Complete values not syncing correctly. This Dataflow fix will not automatically update any environment, it can be downloaded from this page. |
#8977 | Resolved an issue preventing Project level fields from being updated after unlinking an external project. |
#10978 | Resolved a bug where changing the positioning of a Bucket in Project for the Web was not reflected in Altus. |
#11212 | Resolved an issue with text overflow on the Status Summary control. |
#14391 | When the KPI is configured to show more than the default rows, the visual now spans 100% of the available horizontal space. |
#15298 | Resolved an issue where tasks synchronised from Project for the web were not being correctly updated into Altus if they were outdented to become top level tasks. |
#22587 | Resolved an issue where Unassigned Resource assignments were not being filtered out correctly in the Project Online Task Dataflow, causing Unassigned Resource to be created. |
#22591 | The Delete button is now hidden on the task form when viewing a task published from MS Project. |
#9904 | The percent complete on the task list now renders as a progress bar. |
#10861 | Resolved an issue where tasks synchronised from external systems could be marked as complete from the Kanban task view. |
#13164 | Resolved an issue whereby effort values were not being reset on a Project upon linking it to a Planner Plan. |
#15298 | Resolved an issue where tasks synchronised from Project for the web were not being correctly updated into Altus if they were outdented to become top level tasks. |
#18607 | Addressed minor style issue in Timesheet search box overlapping status banner. |
#22086 | Addressed an issue where editing a newly added task to the Altus schedule would not open the correct task in the dialog after saving. |
#22273 | Resolved an issue where the expand/collapse header button was defaulting to the wrong state in the Add Task dialog for Timesheets. |
#22274 | Resolved an issue where long project names were breaking the formatting of the Add Task dialog in Timesheets. |
#22276 | Configured Projects tab on the Program form to show all aligned Projects regardless of their Status value. |
#22277 | Configured Projects tab on the Portfolio form to show all aligned Projects regardless of their Status value. |
#22279 | Configured Programs tab on the Portfolio form to show all aligned Programs regardless of their Status value. |
#22619 | Resolved an issue whereby Resource to Finance Sync was failing when Fiscal Periods were present in an environment but did not cover in entirety the dates of a Resource Plan. |
#24087 | Fixed an issue where Submit for Approval button in Timesheet would sometimes flicker when typing values in Timesheet grid. |
#24095 | Resolved an issue where assigning a resource to a task via form in some situations could cause resource assignment to get removed. |
We acknowledge Aboriginal and Torres Strait Islander peoples as the First Australians and Traditional Custodians of the lands where we live, learn, and work and recognise their continuing contribution to caring for country.